![]() |
|
|
To stabilize the Saskatchewan Legislative
Building, construction crews installed approximately 1,800 piles under the Dome, North,
South and East Wings of the structure. The installation of these piles was carried out
using a process known as underpinning. This page outlines the underpinning process and
provides photos of the work carried out in this phase of the project.
Construction crews excavated earth from under the Dome, North, South and East Wings of the building using bobcats to do a majority of the digging. The excavation below the building occurred in stages. Piles were first installed near the access ramp on the east side of the building. From there, crews worked their way towards the Dome and then to the north and south areas of the building. Pathways excavated under the building provided crews sufficient space to install the new piles.Photos linked below show the excavation and pile installation. Once underground, construction crews installed the pre-cast concrete piles. The piles were installed by hydraulically jacking one-metre pre-cast concrete pile sections into the underlying subsoil. The building's foundation was used as a reaction point (basically a pressure point), for pushing the piles into the earth below. Additional pre-cast concrete pile sections were then added on to the lower section. Jacking continued until the sufficient number of pile sections required to meet specifications were installed. Some original piles were removed to make way for new piles while the majority remain. The pre-cast concrete piles were then encased in concrete. The underpinning portion of this project, as well as phase II, followed a strict heritage conservation approach to ensure the historical integrity of the building is retained. Here you will find photographs of construction crews excavating earth from below the Saskatchewan Legislative Building and installing the new pre-cast concrete piles. You can link to the various work that took place under each wing by clicking on the following links or selecting the correspodning section from the design drawing. East Wing North Wing Centre Core South Wing Pile Construction Approximately 24,300 one metre (three- foot) long pre-cast concrete pile segments were constructed during the course of the underpinning project. Based upon an average pile depth of 13.5 metres ( 41 feet), approximately 80,000 feet of pile segments or 24 kilometers (15 miles) were cast. Each batch of concrete was tested to ensure that adequate strength was developed. Concrete strength was checked at seven, 14 and 28 days with the first two tests monitoring the strength development. The 28 day test verifies the ultimate strength of the pile. After 28 days, the pile segments were sent to the building and installed. The series of photographs below illustrate the manufacturing process in greater detail.
How many piles currently exist under the
entire building? How many piles were installed during the
restoration project? How deep are the old piles? How deep were the new piles driven into
the ground? Is this the first time since 1908 new
piles have been installed? Overview
| Updates | History | Visual Tour | What's New |
Copyright © 2002 [Saskatchewan
Property Management Corporation]. All rights reserved.
20 April, 2001